SEBI's modifications to guidelines concerning Business Continuity Plan (BCP) and Disaster Recovery (DR) systems for Market Infrastructure Institutions (MIIs), such as Stock Exchanges, Clearing Corporations, and Depositories
Near Site (NS) Requirement :
Stock Exchanges : Must have a Near Site (NS) in addition to a Disaster Recovery Site (DRS) to ensure near-zero data loss.
Clearing Corporations & Depositories : NS must ensure zero data loss.
Manpower at DRS : Expertise at the DRS must be equivalent to that at the Primary Data Center (PDC), enabling independent operations at short notice.
Recovery Point Objective (RPO) :The RPO, which determines the maximum tolerable data loss, should be near zero. There should be a documented process for data reconciliation when resuming operations from DRS or other sites.
Solution Architecture :
Stock Exchanges : PDC, DRS, and NS must ensure high availability, fault tolerance, no single point of failure, near-zero data loss, and data integrity.
Clearing Corporations & Depositories : The same, but with a requirement for zero data loss.
Replication :
Stock Exchanges : Synchronous replication between PDC and NS for near-zero data loss; asynchronous replication between PDC and DRS.
Clearing Corporations & Depositories : Synchronous replication between PDC and NS for zero data loss; asynchronous between PDC and DRS. Link-
View Circular